Twinfield has three dimension levels; Projects are on the third dimension.

Level 1 consists of your Balance Sheet and Profit & Loss codes.

Level 2 is used to further specify your A/P and A/R accounts into individual customers and suppliers. Level 2 is also used to allow further analysis of G/L accounts into cost centres.

Level 3 provides further analysis for the Projects and Asset Module. 

     
Select ‘Financial Professionals from the ‘menu bar’ then click on ‘Dimensions’.

clipboard_e79b858a082d63655c2cb4cd8460932a7.png

  Click ‘First free code ‘.

clipboard_e774dcb46dabf0ce2a2a96d49de595af6.png

clipboard_e4eba405b1ea31a6da8346e171d27c3a7.png

Click ‘Next’.

Type the name of the Project.       
‘Save’ Changes
 

Please note: Project codes can be link to a cost centre.

 